Why this matters
Nobody goes up until the plan says what holds the worker at the top of the ladder, because that is the point neither set of rules reaches on its own. The ladder standard governs the ladder. The fall protection standard governs the roof. The move between them - the two seconds where a person is leaving three points of contact, stepping onto a surface they cannot see the condition of, at an edge with the least clearance anywhere on the building - belongs to whichever of those two systems somebody deliberately extended to cover it. If nobody did, it is unprotected, and it is unprotected at the exact moment the worker's hands are busiest.
This card is not a ladder tutorial. The library already carries ladder setting, load ratings, and why the top of a ladder is not for standing on. What follows is the access plan itself, treated as a document with named fields, and then one filled in for a real call.
The ten fields, and what each one is protecting against
Field 1. Which Part applies. Construction fall protection triggers at 29 CFR 1926.501; general industry at 29 CFR 1910.28, and the heights genuinely differ. Servicing an existing rooftop unit is usually maintenance and lands in 1910; replacing it, or building anything, lands in 1926. The line is fact-specific and a mixed scope is common, so where a job carries both, plan to the more protective of the two requirements, which is the conservative direction and costs you nothing on a job you were already rigging for.
Field 2. The landing surface, verified before anyone commits weight. What the roof deck is, how old, whether it carries fragile elements, and how you established that. Established means from the building's records, from a look from an adjacent elevated position, or from someone who has been up there - not from the colour of it seen from a ladder. If you cannot establish it, the surface is treated as fragile and the plan changes shape entirely, which a sibling card covers.
Field 3. The ladder base. Level, firm, not on a soft shoulder, not on a slab edge, not in a doorway swing. If the base moves, everything above it is decoration.
Field 4. The ladder set at the top. For construction, 29 CFR 1926.1053(b) requires the side rails of a portable ladder used to access an upper landing to extend at least 3 ft above the landing surface; general industry carries the same 3 ft extension for portable ladders at 29 CFR 1910.23(c). That extension is not for the ladder, it is a handhold at the height where the worker's centre of mass crosses the edge. Where the extension cannot be provided, the standard's alternative is a grab device, and a parapet is not automatically one.
Field 5. What secures the ladder, and who did it. Tied off at the top, or secured at the base, or footed by a second person who stays there for the whole transition in both directions. Name which. "It was against the wall" is not an entry.
Field 6. Hands, and what is in them. Nothing. Tools, a bag, a cylinder, a sheet of anything goes up separately on a hand line or a hoist, because a worker carrying one item has two points of contact at the moment they need three.
Field 7. The connection order. Connected before leaving the ladder, still connected until behind a rail or beyond the applicable distance from the edge. This is the whole point of the field. A worker who steps onto the roof and then walks to the anchor to clip in has crossed the edge zone unprotected in both directions, and the walk back at the end of the day is the one people do tired.
Field 8. The anchorage, and what makes it one. A fall-protection anchorage under 29 CFR 1926.502(d) must be independent of any anchorage used to support or suspend platforms and capable of supporting at least 5,000 lb per attached worker, or be part of a complete system designed and used under the supervision of a qualified person maintaining a safety factor of at least two; general industry carries the equivalent at 29 CFR 1910.140(c). This is a different rating basis from the concrete fixture anchors this library covers elsewhere for hanging equipment, and the two are not interchangeable - a fastener sized to hold a unit's static weight has no fall-arrest rating, and a lifeline tied to one is tied to nothing. Curbs, vents, pipe stands and the unit itself are not anchorages unless someone qualified has said so in writing.
Field 9. Clearance at the access point. The eave is the worst place on the roof for clearance, because the anchorage is usually farthest away and lowest relative to the worker, and because a fall there goes over the edge rather than onto the deck. The full stack-up and why people compute it short is covered in a sibling card; the field here is the number and where the anchorage sat when it was computed. If the clearance at the access point does not close, arrest is not the answer at that point and restraint or a rail is.
Field 10. Rescue. Who, with what, and how quickly. 29 CFR 1926.502(d) requires prompt rescue or the means for a worker to rescue themselves. A worker suspended in a harness is on a clock, and "call the fire department" is a plan only if you have confirmed the response and the access.
The geometry of the transition
anchorage, above and inboard
*
|
|
parapet or edge |
=========================== roof deck
| ^
| | 3 ft of side rail above
| | the landing, used as the
| | handhold across the edge
| ===== top of ladder
| ///
| /// ladder at roughly a
| /// 4 to 1 rise to base
| /// offset
|///
---+---------------------------- grade
ladder base, level and secured
Two things the drawing carries that the prose does not. The handhold is above the landing, not at it, which is why the extension is not optional. And the anchorage sits above and inboard of the transition point, because an anchorage at or below the worker's feet turns a short fall into a long one.
The plan, filled in for one call
A packaged rooftop unit on a low-slope commercial building, one worker, replacing a failed blower motor, roof height about 18 ft, no permanent access ladder, no perimeter guardrail, an unfenced eave along the whole approach side.
| Field | Entry |
|---|---|
| 1. Part | Repair of existing equipment, so general industry, 29 CFR 1910.28. Trigger is 4 ft, and the roof is well past it. Noted that if the scope grows to a unit replacement it becomes construction under 1926.501 and the plan is re-run. |
| 2. Landing surface | Steel deck with rigid board and membrane, confirmed by the building's roof records and by the facility manager, who has walked it. Two curbed skylights on the far side, outside the work path, treated as holes. |
| 3. Ladder base | Concrete apron, level, clear of the door swing, cones set. |
| 4. Ladder top | Extension ladder set with 3 ft of rail above the parapet, giving a handhold at chest height on the step-across. |
| 5. Secured | Tied off at the top to a structural attachment the facility manager identified, tied before the first full ascent by a worker footed from below. |
| 6. Hands | Empty both directions. Motor, tools and the replacement capacitor go up and come down on a hand line. |
| 7. Connection order | Anchor connector installed and lanyard clipped from the ladder, before the step-across. Disconnect only after returning to the ladder with both hands on the rails. |
| 8. Anchorage | A roof anchor already installed on the building with documentation on file showing it meets the 5,000 lb criterion. The unit's own curb was considered and rejected: nobody has rated it. |
| 9. Clearance | Anchorage stands above the worker's dorsal D-ring at the access point. Clearance computed against the stack-up in the sibling card and it closes at that anchor. It would not close from an anchor at deck level, which is why the deck-level tie point on the far curb was not used. |
| 10. Rescue | Second worker on site, on the ground, with the ladder footed, radio contact, and a plan to bring the ladder to a suspended worker rather than wait. |
Three fields did work here that a shorter plan would have skipped.
Field 8 rejected the equipment curb. That is the single most common improvised anchorage on a commercial roof and it fails the rating question rather than the strength question: nobody has established what it holds, and the standard's alternative route requires a qualified person's design, not a confident opinion. The failure mode is that a curb will hold a static worker perfectly well for years and then not hold an arrest force, and the difference between the two is roughly an order of magnitude.
Field 9 rejected the far tie point on clearance grounds even though it is a rated anchor. Anchor height is the term people leave out, and it moves the answer more than any other term in the stack. The same rated anchor produces a system that works at chest height and one that does not close at deck level, and the reason is that every foot the anchorage drops is a foot of free fall added before the arrest even begins. If the clearance does not close, the answer is restraint - a tether short enough that the worker cannot reach the edge - or a rail, not a longer lanyard.
Field 7 is the one that gets written and then not done. Connected before leaving the ladder means the connection is made while three points of contact are still available, which in practice means the anchor connector was placed on a prior trip or by someone already protected. A plan that says "clip in on the roof" has moved the exposure rather than removed it, and the worker will do what the plan describes.
What changes the plan
A hatch instead of an eave. A hatch removes the edge from the transition and replaces it with a hole in the roof, which needs its own protection while it is open, and a fixed ladder below it with its own requirements. It is a better transition, and it is not a free one.
A parapet high enough to serve as a rail. Where a parapet meets the guardrail dimensional criteria of the applicable Part, it protects the edge and the transition changes from an arrest problem to a climb-over problem. Measure it rather than eyeballing it, and remember that the height that counts is measured from the walking surface on the roof side, which is often several inches higher than the outside face suggests.
Wind, or anything that takes the traction off the deck: ice, frost, a wet membrane. Those are the two conditions that close the job rather than modify the plan. A worker carrying a panel at an edge in wind is carrying a sail, and a single-ply membrane with morning dew on it has almost no traction at exactly the point where traction is what makes the plan survivable. Reschedule; there is no technique that substitutes.
Confirming the plan was followed, not just written
The tell is physical rather than documentary. At the end of the job, look at where the anchor connector is. If it is coiled on the roof deck near the hatch or the ladder head, the connection order was followed. If it is still hanging at the work position twenty feet inboard, the worker walked out unprotected to reach it and walked back the same way, whatever the plan said.
Second tell: the hand line. If it is still bundled in the truck at the end of a job that moved a motor, something went up a ladder in somebody's hand.
References
- 29 CFR 1910.28 and 29 CFR 1926.501, for the general industry and construction fall protection triggers, which are not the same height.
- 29 CFR 1926.502(d) and 29 CFR 1910.140, for personal fall arrest system criteria including anchorage strength and prompt rescue.
- 29 CFR 1926.1053(b) and 29 CFR 1910.23(c), for portable ladder requirements including the 3 ft extension above a landing surface.
- See related: the library's cards on computing fall clearance, on swing fall, on fall restraint, on what a guardrail has to withstand, and on fragile roof surfaces.